LivingInsider Report2017-02-23 11:16:29
Connection

 

 

Construction began in June 2016. Most recently, the construction of the road connecting Ratchaphruek Road - Kanchanaphisek Road (North-South alignment) by the Department of Rural Highways (DRH) has been progressing well.

 


"Pisak Chitwiriyawasin" Director-General of the Department of Rural Highways, revealed that after the Department completed the construction of the connecting road between Ratchaphruek Road - Kanchanaphisek Road (East-West alignment) including a U-turn bridge, which is a new network helping to enhance transportation on the western side of the Chao Phraya River to be more complete, allowing convenient travel from Ratchaphruek Road and Chaiphruek Road to Kanchanaphisek Road, reducing travel distance and time.
 


And to make the network more complete, the Department is currently constructing the connecting road between Ratchaphruek Road - Kanchanaphisek Road (North-South alignment), with a total distance of 14.7 km. Currently, overall progress is approximately 20%, with ongoing work on sand filling for road embankments, bored pile construction, bridge pile driving, and foundation construction. The construction period is 900 days, with the contract starting on June 1, 2016, and the scheduled completion date of November 17, 2018.
 

 

 

 

The construction is divided into 4 contracts, with Unique Engineering and Construction Public Company Limited as the contractor, with a construction cost of 6,759 million baht. Divided into Contract 1 (Section NS1): construction of asphalt concrete road, 6 lanes both directions, distance of 5.2 km, including construction of Khun Maha Thai interchange, 1 location, construction of bridge over Khlong Phra Udom, 1 location, construction of bridge over Khlong Ko Kriang, 1 location, construction of pedestrian overpass, 1 location, progress of 20.14%, 1.74% ahead of schedule.
 


Contract 2 (Section NS2): construction of asphalt concrete road, 6 lanes both directions, distance of 2.8 km, including construction of Phraifaha interchange, 1 location, construction of pedestrian overpass, 1 location, progress of 20.34%, 9.98% ahead of schedule.
 


Contract 3 (Section NS3): construction of asphalt concrete road, 6 lanes both directions, distance of 4.322 km, including construction of Pathum Thani interchange, 1 location, construction of bridge over Khlong Bang Luang, 1 location, construction of bridge over Khlong Mahayotha, 1 location, progress of 14.88%, 4.69% ahead of schedule.
 

 

Contract 4 (Section CD Road): construction of asphalt concrete road, 6 lanes both directions, distance of 2.4 km, including construction of Bang Pho Tai interchange, 1 location, construction of bridge over the intersection of the cross road with CD Road, 1 location, construction of bridge over Khlong Bang Pho Tai, 1 location, construction of bridge over Khlong Tan, 1 location.
 


Construction of bridge over Khlong Mai, 1 location, construction of bridge on CD Road, 1 location, progress of 20.86%, 3.55% behind schedule.
 


"All 4 contracts are large-scale projects, the first in which the Department designed the asphalt pavement using para-asphalt concrete to promote and support the use of para rubber in construction in accordance with government policy."
 


Once completed, this will further enhance the connectivity of the traffic network in northern Bangkok and the metropolitan area.

 

 

Photos and news courtesy of Prachachat Business

 

 

http://www.prachachat.net/news_detail.php?newsid=1487762626

 

 

 

LivingInsider Report
LivingInsider ReportLast update 2017-02-23

>> Follow us for the latest news <<

Add friend

Never miss important news just add us as a friend on LINE @livinginsider here

Article Other