Landfilling for house constructionis an important step before construction begins, but if done incorrectly, it can lead to many problems, such as a settling house, soil slides, or impacts on neighbors. Land filling that is not done in accordance with the law may also cost you both money and time to fix. But how can you do it legally and safely? This article has the answers for you.

Legal provisions regardingland fillingfor house construction

Legal provisions regarding land filling for house construction

Filling land for house construction is an important step that must strictly follow theland filling law, in accordance with theLand Excavation and Land Filling Act B.E. 2543 (2000), with the following key details:

Landfilling 

  • Land filling exceeding 3 meters must be reported to the local authority and comply with the prescribed conditions, such as preparing plans and hiring a supervising engineer
  • Land filling not exceeding 3 meters must include measures to prevent soil collapse, to avoid causing trouble to neighbors
  • If higher than 2 meters above another person’s land, plans are required along with structural calculation reports certified and signed by a supervising civil engineer. If the structure is lower than 2 meters, certification from a civil engineer is not required.
  • Filling land 5 meters high requires supervision by an expert civil engineer for safety and compliance with the law
  • Prohibited at night According to the law, land filling at night is not allowed unless a permit is obtained
  • Install reflective signs Signs must be posted to indicate hazards from the land filling
  • Soil compaction After filling the land, the soil must be compacted firmly to prevent subsidence
  • Has a license and land reclamation plansfor land fillingthat are correct

Soil Excavation 

  • Check the excavation limits Check whether the excavation depth exceeds 3 meters or whether the pit opening area exceeds 10,000 square meters. If it exceeds these criteria, a permit must be obtained
  • Areas suitable for excavation Check whether the area where you want to excavate soil is in a controlled zone or an area at risk as specified by law
  • Excavation not deeper than 3 meters If excavation is carried out near another person's property boundary at a distance of less than twice the depth, soil collapse must be prevented 
  • Prohibited at night According to the law, land filling cannot be done at night unless there is a permit
  • Install reflective signs Signs must be posted to indicate the hazards of land filling
  • Has a license and plans for excavation that are correct in accordance withthe land filling law

3 Key Issues That Require Attention RegardingLand Filling

Land fillingis the process of raising the level of an area, which is part of constructing houses, buildings, or improvingsecond-hand houses and the surrounding landscape. However, land filling must comply with relevant laws and regulations to prevent impacts on the environment and the safety of nearby property and people. Let’s take a look at the 3 key issues that must be considered when filling land legally.

When You Need to Excavate Soil Deeper Than 3 Meters

If you need to excavate soil deeper than 3 meters, you must comply with the Soil Excavation and Land Filling Act B.E. 2543 (2000), which requires obtaining permission from relevant authorities such as the SAO (Subdistrict Administrative Organization) or the municipality, since excavation at this depth may affect the soil structure and nearby buildings. In addition, you may need to consult a specialist engineer to plan the excavation and filling in a safe manner and in accordance with standards.

When the Area to Be Excavated Is Less Than 3 Meters Deep

Even if the excavation is not deeper than 3 meters, you must still comply with local laws and regulations, such as managing the excavated soil, preventing soil collapse, and ensuring adequate drainage, to avoid causing impacts on the environment and other people’s property.

Laws on Filling Land Higher Than Adjacent Land

If you want to fill land to a level higher than other people’s land, you must comply with the law on land filling higher than adjacent land as follows

  • Land filling area not exceeding 2,000 square meters You must provide adequate drainage to prevent causing trouble to neighboring landowners.
  • Land filling area exceeding 2,000 square meters You must notify the local authority of the land filling in the prescribed form and have an engineer supervise the work.

Other Issues That Should Not Be Overlooked

  • Changes to the ecosystem Land filling may destroy wildlife habitats and alter the ecosystem of the area.
  • Groundwater contamination If the soil used for filling is contaminated with chemicals or toxic substances, it may cause groundwater contamination and affect the health of people in the community.
  • Blockage of drainage systems If the land filling is not designed with a good drainage system, it may cause flooding problems and affect the daily lives of people in the community.
  • Changes to the landscape Land filling may change the landscape of the area from its original state and affect the beauty of the scenery.

Beforefilling landto build a house, what should you check?

Fillinglandbefore building a house is an important step that requires careful planning in order to obtain a living space that is strong and safe from natural disasters. Therefore, before starting the process, the following information should be verified:

1. Check the ground level of surrounding areas

Checking the ground level of your land and surrounding areas is an important step before filling the land, in order to plan the land filling appropriately and consistently with the surrounding terrain. You should measure the elevation of your land and compare it with your neighbors' land or nearby areas. 

In addition, you should consider the slope of the land. If your land is lower than the surrounding areas, you may need to fill the soil slightly higher to prevent flooding problems, and you should check whether the drainage system in the area is sufficiently efficient.

2. Flooding history of the land in that area

Checking the history of flooding in the area is another important factor to consider before decidingto fill land for building a house You should inquire with local residents or relevant agencies, such as the local administrative organization, to find out the highest flood levels that have occurred in the past. In addition, studying flood risk maps is also useful for assessing the risk of repeated flooding.

Summary offilling land to build a house

Summary of land filling for house construction

Preparing complete informationabout land filling for house constructionbefore filling will help you plan the land filling thoroughly and reduce the risk of future problems. Whether you are building a new house or renovating one, you can follow these steps to ensure a good investment in proper preparation at the first stage, while also giving you a house that is strong and safe in the long run.

 

Livinginsider Report
Livinginsider ReportLast update 2024-09-27

>> Follow us for the latest news <<

Add friend

Never miss important news just add us as a friend on LINE @livinginsider here

Article Other